Installation of a 110 kV double-circuit transmission line with a length of 18.3 km between the “Khindyrystan 110” substation and the “Tezekend 110/35/10 kV” substation;
Installation of a 10 kV transmission line with a length of 12.33 km;
External power supply for a pumping station with a length of 4.32 km;
Installation of a 35 kV double-circuit transmission line on the “Gabala 110 – Zaraghan 35 kV” section;
External power supply for a pumping station with a length of 6.0 km;
Installation of a 110 kV double-circuit transmission line on the “Ganja 330 – Veisli 110 – Naftalan 110 kV” section, with a length of 47.6 km, and installation of a 10 kV transmission line with a length of 12.5 km;
Installation of a 110 kV double-circuit transmission line with a length of 18.3 km;
Installation of a second 110 kV circuit with a length of 45.9 km;
Installation of a 10 kV transmission line with a length of 16.8 km;
Installation of a 35 kV double-circuit cable line with a length of 16.9 km;
Installation of a 110 kV double-circuit transmission line with a length of 1.7 km;
Installation of a 10 kV transmission line with a length of 12.8 km;
Installation of a 6 kV transmission line with a length of 5.9 km;
Installation of a single 35 kV transmission line with a length of 8.9 km, a 10 kV transmission line with a length of 11.6 km, and a 0.4 kV transmission line with a length of 9.8 km;
Installation of a single 35 kV transmission line with a length of 8.9 km, a 10 kV transmission line with a length of 11.6 km, and a 0.4 kV transmission line with a length of 9.8 km;
Installation of a 35 kV double-circuit transmission line with a length of 5.7 km; a 6 kV transmission line with a length of 9.5 km; and a 0.4 kV transmission line with a length of 23.4 km;
Installation of a 10 kV cable line with a length of 32.0 km and 4.8 km; a 0.4 kV cable line with a length of 22.5 km;
Installation of a 10 kV transmission line with a length of 5.5 km and a 0.4 kV cable line with a length of 11.8 km;
Laying of 12.6 km of cable from the 220/110/10 kV “Senaye Govshagy” substation to the 110/10 kV substation;
Laying of a 110 kV double-circuit cable line with a length of 15.6 km (APvPu2g 1*500(g)/95-64/110) and a double-circuit 35 kV cable line;
Installation of an XLPE-150/25 cable line with a length of 5.8 km.
Supports of power
transmission lines
Sumgayit city
Installation of 110 kV cable APVP2Q 1x500(Q)/ 95-64/110 with the length of 14200 p/m
External power supply
Installation of cables 110 kV APVP2Q 1x500(Q)/ 95-64/11C
with the length of 14200 p/m